상세검색
최근 검색어 전체 삭제
다국어입력
즐겨찾기0
학술저널

해양구조물 건조계약상 공사변경(Change Order) 실무에 관한 연구

A Study on several issues related to the Change Order Claims in Offshore EPC Contracts

  • 80
124379.jpg

Recently most of the offshore construction contracts have been in the type of EPC Turnkey contract. Therefore, there would be a lot of Change Order Claims in the course of engineering, procurement and construction. The question of whether it deserve a Change Order is closely linked to the matter of whether it is within the scope of work of Contractor under the offshore construction contract. Since all the outputs of the construction are originated from the design & engineering it is of importance to know who is responsible for the design & engineering. Normally Contractor makes an amendment agreement for the transfer of all responsibilities over the design & engineering after its reviewing the basic design and FEED design delivered by Owner following the contract award. In that point, Contractor definitely has to take over the responsibilities stem from the only design, engineering and information delivered by Owner. If the Contractor’s scope of work described in a prevailing document is obscure or is very widespread it is very necessary for the Contractor to clarify its scope of work in phase of contract negotiation as the Change Order can not be allowed in circumstances where its work is within the Contractor’s work scope under the original offshore construction contract. As effects of Change Order either Contract price could be adjusted or construction period could be extended accordingly. It should be noted that observation of the procedural requirement for Change Order Request is very crucial in order for the Contractor not to be disqualified from that claim. We examine the confusing cases where work from Change Order is within the Contractor’s work scope under the original contract and also considering a few points that Contractor needs to be aware of thereon. In this article, the study on several problems arising practically from Change Order may provide good guidance for Korean shipbuilders who have been recently suffering from heavy deficit due to offshore construction contracts.

Ⅰ. 서론

Ⅱ. 공사변경의 의의 및 그 절차

1. 공사변경의 개념

2. 공사변경과 작업지시권 행사의 남용

Ⅲ. 공사변경과 업무범위(scope of work)의 관계

1. 조선업체의 업무범위

2. 계약내용의 범위 내(內)인지 여부의 판단기준 및 효과

Ⅳ. 공사변경의 효과

1. 계약금액의 변경

2. 인도기일의 연장

Ⅴ. 설계변경과 관련된 구체적인 사례 유형 검토

1. 설계 자체의 하자

2. 발주자요구조건과 도면, 시방서의 불일치

3. 발주자 도면승인의 법적 의미

4. 발주자 지정 품목의 하자 발생시, 책임의 소재

5. 공사변경 시 보상의 범위 문제

Ⅵ. 맺음말

(0)

(0)

로딩중